FREEDOM OF
INFORMATION COMMISSION
OF THE STATE OF
CONNECTICUT
In the Matter of
a Complaint by FINAL
DECISION
Noah H. Starkey,
Complainant
against Docket #FIC 86-61
Town Manager of
Coventry and the Town of Coventry,
Respondents April 9, 1986
The above-captioned matter was heard
as a contested case on March 17, 1986, at which time the complainant and the
respondents appeared and presented testimony, exhibits and argument on the
complaint.
After consideration of the entire
record, the following facts are found:
1. The
respondents are public agencies within the meaning of 1-18a(a), G.S.
2. On
or about September 13, 1984 the respondent town contracted with the State of
Connecticut, Department of Environmental Protection ("DEP") to
construct a pollution treatment system.
The respondent town thereafter contracted with the firm of Fuss &
O'Neill, consulting engineers, for a hydrogeologic study of the proposed site
in Coventry. Pursuant to such contract,
Fuss & O'Neill conducted certain hydrogeologic tests on property owned by
Anna Z. Hawkes.
3. On
or about June 10, 1986 Fuss & O'Neill forwarded to the Water Compliance
Unit of the DEP a 200-page document entitled:
"Hydrogeologic Study of Land Application Site, Coventry,
Connecticut, March, 1985. Revised June
3, 1985." The DEP provided the
complainant with a copy of such report prior to hearing.
4.
On October
15, 1985, the respondent town, acting by and through its Water Pollution
Control Authority pursuant to 7-248, G.S., voted to acquire Ms. Hawkes's
property in Coventry. On or about
October 18, 1985 the respondent town issued a Statement of Compensation and the
property was thereafter acquired by the town through condemnation
proceedings. Ms. Hawkes subsequently
filed an appeal in Superior Court on the issue of compensation, which appeal
was pending on the date of hearing.
Docket #FIC
86-61 Page Two
5. On
January 14, 1986 the complainant made a request of the respondent town manager
for copies of all reports, test results and analyses prepared by Fuss &
O'Neill in connection with Ms. Hawkes's property.
6. By
letter dated January 15, 1986 the respondent town manager informed the
complainant that he had no objection to the release of the information, if such
information existed. The respondent
town manager stated that he had no knowledge of the existence of such
information.
7. By
letter dated January 23, 1986 the town attorney, Abbot B. Schwebel, informed
the complainant that "[n]o tests were done by Fuss & O'Neill to
determine quantities of gravel on site, since it is our opinion gravel is not a
relevant factor in the value of the property since no gravel permit was ever
taken out on the land." Mr.
Schwebel also asked that further questions be posed in the form of a motion on
interrogatories "and we can argue it in front of Judge Kelly, if need
be."
8. By
letter dated January 31, 1986 the complainant made a request of Fuss &
O'Neill for the reports and records referred to at paragraph 5, above.
9. By
letter dated February 10, 1986 Fuss & O'Neill informed the complainant that
his January 31, 1986 letter had been forwarded to the town attorney. The complainant received no further response
from the town attorney.
10. By
letter of complaint filed with the Commission on February 27, 1986 the
complainant appealed the failure of the respondents to provide the requested
records.
11. At
hearing the respondents moved to dismiss the complaint on the ground that the
appeal was not filed within 30 days of an alleged violation of the Freedom of
Information Act. Finding that the
appeal was filed within 30 days of the respondents' failure to respond to the
inquiry referred to them by Fuss & O'Neill, the motion to dismiss was
denied.
12. The
respondents claim that if the requested records exist they are exempted from
disclosure by 1-19(b)(4) and 1-19(b)(7), G.S.
13. It is found that the records sought are
real estate appraisals, engineering or feasibility estimates and evaluations
made for or by an agency relative to the acquisitition of property or to
prospective public supply and construction contracts, within the meaning of
1-19(b)(7), G.S.
Docket #FIC
86-61 Page Three
14. It
is found that although title to Ms. Hawkes's property passed prior to the complainant's
request, such property was, at the time of the complainant's request and on the
date of hearing, the subject of a judicial proceeding to review the fairness of
the compensation offered to Ms. Hawkes by the respondent town.
15. It
is concluded that, as of the date of hearing, not all of the proceedings or
transactions regarding the subject property had been terminated or abandoned.
16. It
is concluded that the records in question are exempted from disclosure by
1-19(b)(7), G.S.
17. It
is not necessary to address other claims of exemption raised by the
respondents.
The following order by the
Commission is hereby recommended on the basis of the record concerning the
above-captioned complaint.
1. The
complaint is dismissed.
Approved by order of the Freedom of
Information Commission at its special meeting of April 9, 1986.
ÿ
Karen J.
Haggett
Clerk of the Commission