FREEDOM OF
INFORMATION COMMISSION
OF THE STATE OF
CONNECTICUT
In the Matter of
a Complaint by FINAL
DECISION
Anna V. Crawford
and the Town f Suffield,
Complainants
against Docket #FIC 88-209
Commissioner,
State of Connecticut Department of Public Works,
Respondent September 28, 1988
The above-captioned matter was heard
as a contested case on July 21, 1988, at which time the complainants and the
respondent appeared, stipulated to certain facts and presented testimony,
exhibits and argument on the complaint.
After consideration of the entire
record, the following facts are found:
1. The
respondent is a public agency within the meaning of 1-18a(a), G.S.
2. On
or about March 14, 1988 the respondent, acting on behalf of the State of
Connecticut Department of Public Works ("DPW"), entered into a
contract with Frederic R. Harris, Inc., a consulting engineering firm, for the
preparation of an Environmental Impact Evaluation on a proposal to locate a
prison in Suffield.
3. On
or about April 25, 1988 the respondent, acting on behalf of the DPW, entered
into a contract with Fletcher- Thompson, Inc., an architectural firm, to design
the prison project.
4. By
letter dated May 9, 1988 the complainants made a request of the respondent for
copies of any and all documents obtained or produced by Frederic R. Harris,
Inc. in preparing the prison EIE, as they became available to or were prepared
by Harris.
5. By
letter dated May 9, 1988 the complainants made a request of the respondent for
copies of any and all documents generated by Fletcher-Thompson, Inc. with
respect to the prison project, as they became available to the DPW.
Docket #FIC
88-209 Page Two
6. By
letter to the complainants dated May 19, 1988 the respondent stated that the
files of the DPW, the Department of Correction and the Office of Policy and
Management were open to the complainants for their inspection, but that none of
such three agencies had received any of the documents or reports
requested. The respondent offered to
keep the complainants updated on the project through meetings with deputy
commissioner Richard Piotrowski.
7. By
letter dated May 25, 1988 the complainants reiterated their requests to the
respondent.
8. By
letter of complaint dated June 1, 1988 and filed with the Commission on June 2,
1988 the complainants appealed the respondent's failure to provide the
requested records.
9. By
letter to the complainants dated June 2, 1988 the respondent stated that the
documents the contractors were required by their contracts to submit would be
accessible to the complainants upon receipt by the State, but that the records
requested were not otherwise public records.
10. By
supplemental letter of complaint dated and filed with the Commission on June 7,
1988, the complainants stated their position that records generated pursuant to
the contracts referred to at paragraphs 2 and 3, above, were public records,
even if not maintained in the files of any state agency.
11. It
is found that the contract between the DPW and Frederic R. Harris, Inc. calls
for the preparation of a preliminary draft report, a draft report, and a final
report, to be submitted to the DPW within agreed-upon time frames. The contract also provides that each report
submitted must document the data collected in connection with certain specified
"tasks," the first task being "data collection."
12. It
is found that the contract between the DPW and Fletcher-Thompson, Inc. calls
for the preparation of drawings and specifications pertaining to a preliminary
design phase and a final design phase, to be submitted to the DPW within
agreed-upon time frames.
13. As
of the date of hearing, the DPW had not received or reviewed any reports or
records from either Frederic R. Harris, Inc. or Fletcher-Thompson, Inc.
Docket #FIC
88-209 Page
Three
14. It
is found that the requested records, generated or collected by Frederic R.
Harris, Inc. and Fletcher-Thompson, Inc. pursuant to contractual agreements
with the DPW, were not, as of the date of hearing, prepared, received or
retained by the respondent or the DPW within the meaning of 1-18a(d), G.S.
15. It
is further found that, under the circumstances, the requested records were not,
as of the date of hearing, owned or used by the respondent or the DPW.
16. It
is concluded that as of the date of the complainants' request, and up to the
date of hearing, the requested records were not public records within the
meaning of 1-18a(d), G.S.
17. It
is further concluded that the respondent's failure to provide access to inspect
or copy such records did not violate 1-15 or 1-19(a), G.S.
The following order by the
Commission is hereby recommended on the basis of the record concerning the
above-captioned complaint.
1. The
complaint is hereby dismissed.
2. The
Commission notes that the above decision is limited strictly to the facts
herein and should under no circumstances be interpreted as an indication that
public records are only those in the custody of a public agency.
Approved by order of the Freedom of
Information Commission at its special meeting of September 28, 1988.
ÿ
Catherine H.
Lynch
Acting Clerk of the Commission